Level 2 Schedule:


L2 Schedule is the Management Summary, also called a Summary Master Schedule (SMS). It is maintained as a summarization of the Level 3 Project Coordination Schedule(s). It represents the overall project as the project is broken down into its major components, and is used for higher-level management reporting.

Frequently developed by the ‘Client’ as part of its commitment plan for the project and then maintained by the contractor.

It can be used to integrate multiple contractors / multiple project schedules for the overall control of a program. It will include the Level 1 information expanded to show activities and major items of capital equipment.

It should demonstrate the driving path for structures and major process systems at the CSI Division Level (e.g., Earthwork, Foundations, Framing, Enclosure, MEP Services, and Process Equipment), based on the project method statement. Audiences for this type of schedule include (but are not limited to) General Managers, Sponsors, and Project Managers.

Oracle Primavera P6 Level 2 schedule as shown in the below figure will open the level 1 and level 2 of your schedule.