L5 Schedule is the Detailed Schedule. It is a further breakdown of the activities of a Level 4 Schedule. The schedule is used to map out the detailed tasks needed to coordinate day-to-day work in a specific area.
Level 5 schedules are developed by workforce supervisors to plan and coordinate their work at the detail level; Workarounds and critical areas can be explored here. Typically, in Bar Charts (Gantt Charts)
The schedules are replaced every 1, 2, or 4 weeks depending on the complexity of the work, typically schedules extend for 1 or 2 weeks beyond the date when the replacement is due (ex: a weekly schedule will extend for 2 weeks and be updated/replaced each week), this encourages continuity of working.
Audiences for this type of schedule include (but are not limited to Superintendents, Team Leaders, Crew Leaders, General Foremen, Foremen, and Sub-foremen.